Scope and tentative Schedule of events:
- Milling of pavement to 2” depth (scheduled for August 21)
- Temporary markings, traffic loop repairs, and adjustments (following the milling, during the weeks of August 21 and August 28)
- Paving top course (September 5)
- Final pavement markings (September 5, tentative)
- Traffic will be limited to northbound only on September 5 between Whalen Road and Liberty Street. Signage will be posted in advance and flaggers will be present to manage traffic flow.
Please direct project questions to MCDOT at (585) 753-7720 or mcdot@monroecounty.gov.